Spokane Valley Home Projects: Finding the Right Permit Application

For most work on a Spokane Valley house, one online portal carries the permit from application to inspection. For some of it, the Valley is not the permit office at all.

The City of Spokane Valley Permit Center issues the building permit and the mechanical and plumbing trade permits. Its own pages state the electrical boundary plainly: electrical permits come from the Washington State Department of Labor and Industries. Sewer permits are a third office again — issued, the Valley’s residential page says, through the Spokane County Utility Department.

This page is for an address inside the Valley’s city limits. A “Spokane, WA” mailing address proves nothing, because the same postal city covers City of Spokane, Valley and unincorporated county addresses: the jurisdiction guide settles which authority applies and the cluster overview routes the rest. Two limits apply here. This page does not decide whether your project needs a permit, and it publishes no fee total; the Valley’s Master Fee Schedule is the current list.

Start with the address, then the project

The Valley is one permit authority among several in the county. Put the address into the county’s parcel dashboard or the jurisdiction guide before you read any checklist: a Valley lot and the lot next door may sit with different authorities.

The Valley also publishes its own permit register. Its public permit search takes an address, a parcel number, an application number or a permit type, and returns results without an account; two searches run on 3 October 2026 — one for a street, one across the register — both answered. The search shows what is on record; it is not proof that unrecorded work never happened, which the permit-history guide covers.

What the Valley’s own pages say needs a permit

The residential page states that permits are required for new single-family homes, new duplexes, new garages and pole buildings, new decks, pools, spas or fences, additions of any square footage to an existing home, duplex or accessory structure, and interior alterations to any of those. The mechanical and plumbing page adds new, altered or replaced mechanical and plumbing fixtures and appliances.

One row of that list does not match another Valley document. The residential page names fences among the projects requiring permits, while the city’s own Residential Fencing Standards handout opens “Although there is no permit for a standard fence, there are guidelines required to be followed”, and then states that a residential fence above seven feet up to eight feet must be permitted and engineered. Both documents are the city’s, published side by side. Ask the Permit Center which applies to your fence rather than assuming either exemption or requirement.

Which office issues which permit

Your project Who issues the permit Where the application goes
New house, addition, interior remodel, deck, garage, accessory structure City of Spokane Valley Permit Center The city’s online portal, or the matching PDF application delivered to City Hall
Mechanical or plumbing fixture or appliance work City of Spokane Valley Permit Center Portal, or the mechanical or plumbing PDF; commercial work may also require plans or calculations
Electrical Washington State Department of Labor & Industries, not the city L&I’s own permit route
Sewer connection or disconnect Spokane County Utility Department A copy of the sewer permit accompanies the Valley building application
New or altered driveway approach, or work in the right of way City of Spokane Valley, Development Engineering and the Permit Center An approach permit or a right-of-way permit, the latter with a traffic control plan
Sprinklers, alarms and other fire systems Spokane Valley Fire District #1 The fire district, alongside the city building permit
Demolition, and asbestos on a renovation or demolition Spokane Regional Clean Air Agency A Notice of Intent; the Valley’s own checklist names it for demolition

The five steps the Valley publishes

  1. Complete the application. The city recommends its online portal, which it says may be processed more quickly, and where an applicant submits, pays, obtains the permit and schedules an inspection. Fillable PDFs remain available for anyone who does not want to use it.
  2. Submit the materials and the fees. Application fees must be paid before the application is processed. Payment is by card through the portal or by telephone, or by check or cash at the counter; the city charges a 2.5% convenience fee on credit-card and online payments, and states it is not charged for checks or cash paid to the Permit Center directly.
  3. Review. Staff review the application and any additional materials, contact the applicant if more is needed, and notify applicants when a permit is approved.
  4. Request inspections as the work proceeds. Inspections are booked through the portal or the Inspection Request Line at 509-720-5350.
  5. Certificate of Occupancy, where it applies. The city prepares a certificate for new buildings and additions once inspection staff and the review agencies have given final approval of every permit on the project.

What the application itself asks for

The Valley’s Residential Construction Permit Application opens with the site address and parcel number, then a checkbox for new construction, addition or remodel, or accessory building. It asks for the owner block with an “owner build” checkbox, a contractor block carrying the Labor & Industries licence number and UBI, and a scope section covering construction type, building height, storeys, total habitable space, main-floor square footage and whether the site sits in a special flood hazard area.

The applicant signs a disclaimer that names three routes under RCW 18.27 — a contractor registered and licensed under that chapter, the registered or legal owner or authorised agent who is not a licensed contractor, or a person otherwise exempt — and confirms that any plans the city requests will be submitted and approved before the application is processed.

Behind that form sits a submittal checklist by project type:

Project What the Valley’s own checklist names
New residential or addition Site plan to the Residential Site Plan Guide; building plans drawn or drafted to scale per the 2021 IRC; truss, beam or joist layout and calculations; mechanical and plumbing application; WSU energy credit worksheets
Interior remodel Floor plan with all rooms labelled; beam calculations where applicable; mechanical and plumbing application
Deck Site plan; joist or beam calculations where applicable; elevation view of deck and stairs; post layout design; engineered plans must be wet stamped; mechanical and plumbing application where applicable
Carports, lean-tos, covers, and other structures Site plan and building plans to scale, plus elevation view; egress windows, window well detail and header sizes appear on the same checklist
Pole building Engineered drawings are required under RCW 18.08.410, and one set must carry an original signature and stamp
Any demolition A Notice of Intent permit from Spokane Regional Clean Air Agency, plus a sewer or septic disconnect permit where applicable

The form also tells applicants to ask the counter for the Residential Code Construction Handout and, on the deck row, for the Deck Building Guide — the Valley’s own documents, worth requesting by name.

Inspections and closing the permit out

Inspection requests made through the portal or the request line before 7 a.m. will generally be performed the same business day; requests after 7 a.m. are scheduled for the next business day. That single cut-off is the city’s own published rule and the field most likely to move a project’s schedule.

A Certificate of Occupancy does not have to be requested: for eligible permits the city states it is generated automatically within 24 hours of the completion of all inspections and conditions, is available in the portal or by email, and carries no additional fee. Occupancy before every condition is finished is a different route. A Temporary Certificate of Occupancy is requested through the building inspector, may need final sign-off from Engineering, Planning, Spokane Valley Fire Department and Spokane Regional Health District, is requested in writing with the permit number and an estimated completion date, and carries a fee set in the Master Fee Schedule. The city’s own wording is blunt: a building is not authorised for occupancy until a certificate signed by the building official is in hand.

Where the Valley’s counter stops

Next step

Write the site address, parcel number, project type, scope in plain words, valuation basis and the drawings you already hold onto one page, then submit through the Valley’s portal or put it in front of Permit Center staff. The cluster overview routes the other offices; the permit-history guide shows what is already on record for the address before you file anything new.

Sources

All pages, handouts and forms opened and read 3 October 2026, except where noted.

Source Used for
City of Spokane Valley, Residential Building Permits: https://www.spokanevalleywa.gov/242/Residential-Building-Permits “Permits are required for any of the following residential projects…” and the project list; the pole-building engineering note citing RCW 18.08.410 with an original signature and stamp; “Sewer permits are issued through the Spokane County Utility Department”; the site-plan examples, fencing standards and pool, hot tub or spa standards links; the 2.5% convenience fee and the payment routes; the Permit Center address, telephone and mailbox
City of Spokane Valley, Apply for a Permit: https://www.spokanevalleywa.gov/227/Apply-for-a-Permit “It is recommended that customers use the Online Permit Portal”; “Applications submitted through the portal may be processed more quickly”; the five application steps; “Application fees must be paid prior to application processing”; the inspection request rule that requests before 7 a.m. will generally be performed the same business day; the Certificate of Occupancy and Temporary Certificate of Occupancy sequence; the Master Fee Schedule link
City of Spokane Valley, Permitting: https://www.spokanevalleywa.gov/181/Permitting The Permit Center’s permit families — residential building, commercial building, mechanical and plumbing, other permits (demolition, grading, right of way, roofing, signage, manufactured homes), accessory dwelling units, inspections; the Building Official contact
City of Spokane Valley, Residential Construction Permit Application (PDF): https://www.spokanevalleywa.gov/DocumentCenter/View/659/Residential-Permit-Application-PDF The form’s fields — site address, parcel number, owner block with the owner-build checkbox, contractor block with the Labor & Industries licence number and UBI, scope of work, construction type, building height, storeys, habitable space, main floor square footage, special-flood-hazard-area question; the RCW 18.27 applicant disclaimer; the per-project submittal checklist for new residential and additions, interior remodels, decks, carports and covers; the Notice of Intent from Spokane Clean Air and the sewer or septic disconnect permit; “Ask for the Residential Code Construction Handout” and “Make sure to ask for Deck Building Guide”
City of Spokane Valley, Mechanical / Plumbing Permits: https://www.spokanevalleywa.gov/230/Mechanical-Plumbing-Permits “Work Requiring a Mechanical or Plumbing Permit” — new, altered and replaced fixtures and appliances; the portal and PDF routes; the note that commercial mechanical or plumbing work may require plans or calculations; the fee-payment rule
City of Spokane Valley, Building Inspections: https://www.spokanevalleywa.gov/228/Building-Inspections The Inspection Request Line at 509-720-5350 and the same-day rule for requests received before 7 a.m.
City of Spokane Valley, Certificate of Occupancy handout (PDF): https://www.spokanevalleywa.gov/DocumentCenter/View/5102 Automatic C of O within 24 hours of completed inspections and conditions at no additional fee; the seven-step TCO request; the four agencies that may require TCO sign-off; “You are not authorized to occupy the building until you have received a CO or TCO document signed by the building official”; permitcenter@spokanevalleywa.gov
City of Spokane Valley, Transforming Your Space (business resources): https://www.spokanevalleywa.gov/536/Transforming-Your-Space “Spokane Valley issues trade permits for mechanical and plumbing.” / “Washington State Department of Labor and Industries permits for electrical.”; “permits for electrical work are issued by the Washington State Department of Labor and Industries”; “Your contractors will also need to hold City of Spokane Valley business licenses to pull permits.”; Spokane Regional Clean Air Agency permits for asbestos removal and demolition
City of Spokane Valley, Residential Fencing Standards handout (PDF): https://www.spokanevalleywa.gov/DocumentCenter/View/504/Residential-Fencing-Standards-PDF “Although there is no permit for a standard fence, there are guidelines required to be followed…”; the statement that a residential fence above seven feet up to eight feet must be permitted and engineered; SVMC 22.70.020 as the cited authority
City of Spokane Valley, Residential Pool, Hot Tub or Spa Standards handout (PDF): https://www.spokanevalleywa.gov/DocumentCenter/View/503/Residential-Pool-Hot-Tub-or-Spa-Standards-PDF The submittal list for pools and spas — site plan, plans or design with in-ground engineered and above-ground manufacturer’s specifications, barrier details; the note that additional mechanical and plumbing permits may be required; the Permit Center telephone and mailbox
City of Spokane Valley, Development Engineering Design Standards and Codes: https://www.spokanevalleywa.gov/514/Development-Engineering-Design-Standards The Division’s role in design review and construction inspection of the engineering components of private development; SVMC Title 22 and 24; the fencing, screening and landscaping and lighting code references
City of Spokane Valley, Approach Permits: https://www.spokanevalleywa.gov/246/Approach-Permits A driveway approach is the transition where a private driveway meets a public or private street; approaches on private streets do not require a permit; otherwise a driveway approach permit is required
City of Spokane Valley, Right-of-Way Permits: https://www.spokanevalleywa.gov/251/Right-of-Way-Permits The definition of right of way; the permit requirement unless exempt under SVMC 9.50.010; the traffic control plan requirement
City of Spokane Valley Public Portal (permit search and application): https://ci-spokanevalley-wa.smartgovcommunity.com/ApplicationPublic/ApplicationHome and https://ci-spokanevalley-wa.smartgovcommunity.com/ApplicationPublic/ApplicationSearchAdvanced The live public register and its search fields; the permit-type list, including the Millwood-named types; two searches run on 3 October 2026 (a street search returning 12 records and a blank register search)
Washington State Department of Labor & Industries, Electrical Permits, Fees & Inspections: https://www.lni.wa.gov/licensing-permits/electrical/electrical-permits-fees-and-inspections/ “You must get your electrical permit and inspection from the correct jurisdiction: If your jobsite is in a city that does their own permits and inspections… you must purchase the permit and request the inspection from them. All other jobsites in Washington are permitted and inspected by L&I.”; electrical work requires a permit and inspection; L&I inspects to the 2023 National Electrical Code
Spokane Valley Permit Center: City Hall, 10210 E Sprague Avenue, Spokane Valley, WA 99206 · 509-720-5240 · Inspection Request Line 509-720-5350 · Building Official 509-720-5305 The inquiry routes a reader uses after reading this page

Report an error or a change you have spotted: use our contact page.


J03 · Local permits and property researchIntent: OrientSources checked October 3, 2026Published October 3, 2026

This site does not give property-specific legal, engineering, tax, or medical advice. Verify rules, programmes, and provider details with the responsible authority. Spotted an error? Tell us.